Coal Ministry rejects ‘No Takers’ claim, says TFL, NTPC apply for gasification scheme
Talcher Fertilisers Ltd is already working on implementing a coal-based ammonia-urea gasification complex, expected to be commissioned in FY 2027-28.
Account subscription benefits alongside Premium Stories, Editorials, Opinions and more.
Unlock these with Subscription
The View From India Looking at World Affairs from the Indian perspective.
First Day First Show News and reviews from the world of cinema and streaming.
Today's Cache Your download of the top 5 technology stories of the day.
Science For All The weekly newsletter from science writers takes the jargon out of science and puts the fun in!
Data Point Decoding the headlines with facts, figures, and numbers
THEdge At the cutting edge of education and careers
Health Matters Ramya Kannan writes to you on getting to good health, and staying there
Gender Agenda Stories from beyond the binary.
The Hindu On Books Books of the week, reviews, excerpts, new titles and features.
Updated - September 05, 2026 08:37 pm IST - NEW DELHI
The Ministry of Coal on Saturday rejected reports that the Centre’s coal gasification incentive scheme had failed to attract applicants, saying Talcher Fertilisers Ltd (TFL) and NTPC Ltd have already submitted their applications ahead of the September 7 deadline.
“Based on discussions with stakeholders, the Ministry has been informed that TFL and NTPC Ltd have already submitted their respective applications through the online portal.
This itself demonstrates that the assertion that the scheme has received ‘no takers’ is factually incorrect,” the ministry said in a statement.
The Union Cabinet had on May 13 approved a ₹37,500 crore package aimed at promoting surface coal and lignite gasification in the country.
The request for proposal (RfP) was subsequently issued, with the current application window closing on September 7.
TFL, a joint venture involving Rashtriya Chemicals and Fertilisers, Coal India, GAIL and Fertiliser Corporation of India, is already implementing a coal-based ammonia-urea gasification complex in Talcher, Odisha.
The project has an estimated investment of ₹13,277 crore and is expected to be commissioned in FY28.
The ministry said several other prospective applicants are also in communication with it, with their projects at various stages of preparation and application finalisation.
To facilitate participation in capital-intensive gasification projects, the government has adopted a rolling-round mechanism for applications.
Once the current application window closes, the next round will open the following day and remain available for two months.
“The rolling-round mechanism has been deliberately incorporated in view of the substantial preparation and investment requirements associated with large-scale coal/lignite gasification projects,” the ministry said.
coal / economy, business and finance / minerals (general) / energy resources / energy and resource
Terms & conditions | Institutional Subscriber
Comments have to be in English, and in full sentences.
They cannot be abusive or personal.
Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform.
If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles.
If you do not have an account please register and login to post comments.
Users can access their older comments by logging into their accounts on Vuukle.
Full detailed coverage is shown on the council website above. Source attribution: The Hindu – Business.
Back to all council news